Reston Association's resale disclosure package includes a resale certificate with a financial statement for the property, the results of an exterior inspection, the governing documents, the current operating and capital budget, minutes from a recent Board meeting, and the reserve study. The package is available through WelcomeLink.

Most buyers flip to the assessment line, see a modest annual figure and move on. For 2027 that figure is $900 per property. RA's October 8 board packet carries a five-year staff forecast that puts it at $954 in 2028 and $1,087 by 2031.

The package and Reston's associations

The board has already set the 2027 assessment, and it is due March 1, 2027.

The inspection matters as much as the money. RA staff review the full exterior of the home and list any use, maintenance and design violations they see.

Reston has more than 200 sub-neighborhood associations, according to RA's cluster and condo directory, revised October 1, 2026. RA describes each cluster or condominium as an independent entity with its own governing documents, board, rules, assessments and services. It also notes that most detached homes are not in clusters. RA's package covers RA only.

Va. Code § 55.1-2316 allows associations to charge fees for preparation, delivery, inspection and post-closing work and requires associations to publish their fee schedules.

How 2027 came in at $10

The RA Board of Directors adopted the 2027 budget on October 22. That puts the assessment at $900, up from $890 in 2026, which RA calls a 1% increase. As FFXnow reported, the vote came earlier than in past years, when the budget was usually adopted in November.

Two things kept the increase small. The first was more than $550,000 in operating savings. FFXnow listed the cuts: the chief operating officer position was eliminated, the Activities Guide went mostly digital, and spending on technology and seasonal staff came down. RA puts the savings from the digital guide alone at about $100,000 a year in printing and postage.

The second was about $400,000 in offsets: investment earnings, projects that came in under budget, canceled projects, and contributions from the Friends of Reston for the Walker Nature Center and RA's trail maintenance program. RA says these offsets reduced the assessment by about $18 per household. The October 8 budget packet sets the figure at $397,000 and lowers the 2027 capital contribution target to $3.15 million, rising to $3.75 million in 2029.

Savings from the cuts can carry into future years. Offsets have to be found again every year. The packet's forecast shows them shrinking.

What RA's forecast shows next

Starting last year, RA staff have built a notional five-year forecast of the budget and capital reserve. This is the version in the October 8, 2026 packet, which shows the 2027 draft budget at $900, the same figure the board later adopted.

Year Assessment per property Increase Capital offsets
2025 actual $848 3.8% $808K
2026 budget $890 5.0% $692K
2027 $900 1.1% $397K
2028 forecast $954 6.0% $300K
2029 forecast $1,000 4.8% $300K
2030 forecast $1,050 5.0% none
2031 forecast $1,087 3.6% none

The forecast assumes operating expenses rise 4% a year and that about $300,000 a year comes back from investment earnings and canceled or under-budget capital projects. Staff wrote that "conditions will change" and that they hope to find more savings and offsets. None of the years after 2027 is a rate the board has adopted. They are RA's own planning numbers.

Even so, the shape is clear. In this forecast, 2027 has the smallest increase of any year from 2025 through 2031. The 2027 figure works out to $75 a month. The 2031 forecast works out to roughly $91 a month, about 21% above the 2027 assessment.

Where the capital money is scheduled to go

The forecast climbs because the capital plan does. The board approved a 2027–2036 Capital Improvement Plan on October 8. Here is how its projects fall by year, using the packet and FFXnow's coverage:

  1. 2027: a new splash pad at Uplands Pool, a renovation of the Lake Newport tennis courts, and the last year of a three-year project to standardize and upgrade trail markers and signage. The Lake Newport courts will become tennis-only, with no pickleball, and the renovation adds new lighting at the court entrances and repaves the paths. The operating budget also includes $7,500 for a study of lake sediment, meant to understand how it relates to seasonal algae.
  2. 2028: dredging at Hickory Pond Cluster, Bright Pond and Butler Pond, $484,500 in total. The Lake Newport gazebo replacement stays on the schedule for this year.
  3. 2029: Lake Audubon is scheduled for dredging. The plan also holds a placeholder for "RA Office Improvements" until RA decides on the lease for its headquarters at 12001 Sunrise Valley Drive.
  4. 2030: Lake Anne is scheduled for dredging. Together with Lake Audubon, that comes to about $2.7 million. RA's office lease expires at the end of July 2030.
  5. 2031: possible replacement of the lighting around Lake Anne. RA CEO Peter Lusk told FFXnow that replacement parts for the aging lights "can be hard to find" and that no changes are planned before the date in the CIP.

The 2027 projects are small. The dredging years are the expensive ones, and they fall in 2028 through 2030, the same years the forecast assessment rises fastest. The two schedules line up because the capital contribution has to grow to pay for that work.

What this means for a buyer

A home in a cluster or condominium adds a second set of assessments with its own budget. Reading both sets together gives a fuller monthly figure than the RA line alone. Our Reston neighborhood page and the buyers' guide put those costs alongside everything else on a purchase.

This post is general information about RA's published budget and Virginia's resale rules. It is not legal or financial advice, so please confirm the specifics of your own contract with your attorney or settlement professional.

A few questions buyers ask

Is the $1,000 assessment for 2029 decided? No. The board adopted only the 2027 rate. The figures for later years come from a notional staff forecast in the October 8 packet, and RA's staff expect conditions to change.

Does the 2027 budget pay for lake dredging? The 2027 budget pays for a $7,500 sediment study. The dredging is scheduled to start in 2028.

When is the 2027 assessment due? March 1, 2027. RA said in its October 22 announcement that invoices would be mailed in the coming weeks.

If you're weighing a Reston home or getting ready to list one, The Velvel Group can go through the forecast with you. Schedule a consultation.

Let's Find Your Dream Home Together

We pride ourselves in providing personalized solutions that bring our clients closer to their dream properties and enhance their long-term wealth. Contact us today to discuss all your real estate needs!

Follow Us on Instagram